Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Remeasurement in Lump Sum Contract

9 replies [Last post]
Samagata Chakravorty
User offline. Last seen 8 years 13 weeks ago. Offline
Joined: 1 Dec 2005
Posts: 16
Groups: None
hi,
in a lump sum contract,if only the material specification of an original BOQ item is changed(eg instead of bitumen painting cementitious waterproofing is instructed)is it required to remeasure the whole item even if there is no change in the scope quantity wise??? plz throw some light with reference to FIDIC.

Replies

Mike Testro
User offline. Last seen 22 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Lloyd

This is a very old thread and it is not a good idea to tag new topics to a long dead subject.

In future please start a new thread.

It all depends on what your sub-contract says in respect of risk in work volumes.

If it is a fixed price lump sum and the scope of work has not changed then if the quantity of work is different to that priced then you cannot expect a change.

If however the employer has changed the scope of work then you may be able to calculate the difference by add / deduct the quantities.

If the change results in a lesser quantity then there is usually no reduction in time unless it forms part of an overll EoT calculation.

Best regards

Mike Testro

lloyd dayap
User offline. Last seen 13 years 10 weeks ago. Offline
Joined: 14 Jun 2011
Posts: 2
Groups: None

We are a Subcontractor on a back to back basis using GCC contract ( Lump Sum & Unit Rate Basis ).

Our problem is when will be the variation/work considered under remeasurement and under extra . How it will affect the progress say in the original scope IFC drawing the quantity is bigger after issuance of design change by contractor it was change to a lesser quantity.

Anticipating your usual prompt response regarding this matter with thanks.

 

Lloyd

Bolisetti Jogiraju
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 7 Jul 2007
Posts: 32
Groups: None
Hi
Skan Bu !
We have to identify that what type of Contract it is,and the concerned docs.
Check all doc’c according to Cl 5.2 of FIDIC.
secondly,from where you have identified these changes.
no need to remeasure whole,paticular segment is enough.

Hope,you got it.

cheers
Skan Bu
User offline. Last seen 13 years 46 weeks ago. Offline
Joined: 29 May 2006
Posts: 118
Groups: None
Hi Bolisetti,

Thanks

I thought that is the way forward too.
But the Supervising Officer (resident Eng) insist that this is a remeasure contract.
The way I interpret the sub contract :seems to be Add/Omit.
Surely,I do not have to remaesure the whole woeks but pick up the are of change, add & omit.
He seems to think it is my responsibility to remaesure & pay accordingly.
He wouldn’t issue SI or confirm the CVI sent to him & as far as I can see,there are no drgs revision and he had not given me any levels, ie is the existing before excavation & the as build.
What should I do?

Bolisetti Jogiraju
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 7 Jul 2007
Posts: 32
Groups: None
Hi Skan Bu & Samagata
I have joined verr recently to this nice society.
I strongly agreed with Raphael’s reply on this issue.
To Samagata !
If both parties in the contract agreed,the difference of cost due to material change can be added to the contract.

To Skan Bu !
The S/C is bound in line with FIDIC,no extra over for concrete ,only thing is you have to apply ADD/OMIT rule for varied work with Contract rates/Agreed rates.

Cheers
Raphael Adeyemi, ...
User offline. Last seen 9 years 49 weeks ago. Offline
Joined: 23 May 2007
Posts: 51
Hi Samagata,

The FIDIC 1992 Edition clause 53 - valuation of variations stipulates how these issue should be treated. It is a varied work and should be remeasured and priced with a simillar item in the BOQ. Should the nature or the amount of works differs so much from the original contract provision, it is the Engineer’s responsibility to fix the rate or prorate basis from existing rate.
Hope u will find this useful
Hernando Pesca
User offline. Last seen 16 years 49 weeks ago. Offline
Joined: 23 Apr 2007
Posts: 24
Groups: None
Hi Samagata,

If I am a contractor, I will surely re-check the quantity and claim for the material difference. If the contract is lumpsum, contractually you are only entitle for material price (or work) difference in such case. Your claim would only be qty. (orig. scope) x its difference in price.

Regards,

Hernan

Samagata Chakravorty
User offline. Last seen 8 years 13 weeks ago. Offline
Joined: 1 Dec 2005
Posts: 16
Groups: None
in addition to my earlier query, plz note that there is for sure a price adjustment for the change but is it necessary to remeasure the quantity or the exsiting BOQ quantity can be considered while adjusting the price.

thanks
sam
Skan Bu
User offline. Last seen 13 years 46 weeks ago. Offline
Joined: 29 May 2006
Posts: 118
Groups: None
Hi,

Like yourself, I am always confuse regarding whether is remeasure or not.
I am working on a contract where the main contract is Fidic.
The subcontract is also a Fidic with amendment.
The enquiry sent to the Civil work subcontractor is drawings, spec and a BQ (The BQ is produced by the Main Contractor based on the drawings)

Order is eventually given based on their quotation, priced up the BQ (inclusive prelim etc)

On the first day on site, the new drawings showed the drains route had change. The route will cross a concrete foundation and the original BQ do not included excavation in concrete.

Questions:
1) PRINCPLE: Do we remeasure because the work had changed?
2) In such a case, Fidic contract, should it be a Lump Sum pay on completion of the work plus a claim on the extra over excavation in concrete foundation?
3) Pay Lump Sum as order but add & omit?
4) Do any of these phase: "Sub Contract Sum" or "Order Value" or "Tender Sum" OR "Sum" play a part?

Obviusly, the S/C do not want to remeasure but wants to be paid full as order (qty might had decrease)and also claim the excavation in copncrete too.

Would appreciate some logical/certainty explanation.

I think this situation will also answer samagata’s query

thanks