If the thickness of the column is larger than the width of the beam, I think you have a valid reason of claiming the column rate. You can argue that beam tag number ends on the face of the column. It also make easier when you do the quantification so you don’t need to subtract the beam volume on the column volume. You maybe face the same problem on the slab if that is also a separate rate. In case that slab rate is same rate as beam I’m afraid you need to follow the beam rate. Good Luck.
Consider the formwork, measure the formwork for the beam and the concrete and re-bar contained.
Do the same for the column, in other words measure the beam from face of column to face of column. The column is measured from top of slab to top of slab.
I am only a mere planner with no QS training so I may be barking up the wrong tree.
Thanks alot. - You have a valid point. But not all beams maintain their tag when crossing the column, and generally beam widths are smaller than column thickness. Our case, the column has the higher rate than that of the beam.
Yes, it is strange that such condition is not defined in our method of measurement.
Usual computation especially if beams width is larger than thickness of column when it crosses the method of measurement should use a beam rate. It is also clearly shown on the drawing that the beam number/name or beam tag number is the same after crossing the column. You can make an argument by showing the detail drawings and rebar schedule. Lintel beam are normally end from column to column and the column rates prevails. Maybe you can use the detail drawing as reference. Column name or column tag number change on every floor or levels. There should be a heavy civil or building pagination that you can use as another reference. Strange to hear that does not defined in your contract method of measurements especially on bulk quantities that you mentioned.
you have to illustrate it in a detailed manner (if you got the drawings). I dont see any problem with that. Its just a matter of presentation and calculations in terms of cubic meters or whatever.
make a tabulation of the dimensions of your columns and beams (supported by your drawing / detail)
Thanks for replying. - The structural framework of the project is already completed. It is a contractual matter. I am talking about the common volume of concrete when beams intersect the column. Where would that volume be added- to column qty. or to beam? Usually, it is on column.
Right away, anyone would say that it would be a minimal quantity, but not on this project. There is also big difference in their rates.
Our Method of Measurement does not say the delineation of qty. when beams cross the column.
I am looking for a written guideline of a reputable standard.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Andrew/Rodel/Clive,
Thanks...
Andrew, we took a stand just like youve said. It is not a close chapter yet, and I am looking at 70/30% sharing of the common volume.
Regards,
Hernan
Hernan,
If the thickness of the column is larger than the width of the beam, I think you have a valid reason of claiming the column rate. You can argue that beam tag number ends on the face of the column. It also make easier when you do the quantification so you don’t need to subtract the beam volume on the column volume. You maybe face the same problem on the slab if that is also a separate rate. In case that slab rate is same rate as beam I’m afraid you need to follow the beam rate. Good Luck.
Can I make a suggestion?
Consider the formwork, measure the formwork for the beam and the concrete and re-bar contained.
Do the same for the column, in other words measure the beam from face of column to face of column. The column is measured from top of slab to top of slab.
I am only a mere planner with no QS training so I may be barking up the wrong tree.
Rodel,
Thanks alot. - You have a valid point. But not all beams maintain their tag when crossing the column, and generally beam widths are smaller than column thickness. Our case, the column has the higher rate than that of the beam.
Yes, it is strange that such condition is not defined in our method of measurement.
Hernan
Hernan,
Usual computation especially if beams width is larger than thickness of column when it crosses the method of measurement should use a beam rate. It is also clearly shown on the drawing that the beam number/name or beam tag number is the same after crossing the column. You can make an argument by showing the detail drawings and rebar schedule. Lintel beam are normally end from column to column and the column rates prevails. Maybe you can use the detail drawing as reference. Column name or column tag number change on every floor or levels. There should be a heavy civil or building pagination that you can use as another reference. Strange to hear that does not defined in your contract method of measurements especially on bulk quantities that you mentioned.
Rodel
you have to illustrate it in a detailed manner (if you got the drawings). I dont see any problem with that. Its just a matter of presentation and calculations in terms of cubic meters or whatever.
make a tabulation of the dimensions of your columns and beams (supported by your drawing / detail)
Thanks for replying. - The structural framework of the project is already completed. It is a contractual matter. I am talking about the common volume of concrete when beams intersect the column. Where would that volume be added- to column qty. or to beam? Usually, it is on column.
Right away, anyone would say that it would be a minimal quantity, but not on this project. There is also big difference in their rates.
Our Method of Measurement does not say the delineation of qty. when beams cross the column.
I am looking for a written guideline of a reputable standard.
Thanks once again.
what do you mean? are you doing a structural design or just taking the quantity of reinforced concrete?
if it is design, you do some structural calculations!
if it is just quantities, then check the details of your drawings!