Line of Balance

3 replies [Last post]
Lo Gary
User offline. Last seen 1 year 5 weeks ago. Offline
Joined: 7 Feb 2010
Posts: 52
Groups: None

Dear,

 

Could I just print the line of balance graph instead of print the Gannt Chart together with the line of balance?

 

 

 

Regards,

 

Gary Lo

Replies

Lo Gary
User offline. Last seen 1 year 5 weeks ago. Offline
Joined: 7 Feb 2010
Posts: 52
Groups: None

Dear,

 

Could I export the line of balance graph to Excel to make modification?

 

 

Regards,

 

Gary Lo

Lo Gary
User offline. Last seen 1 year 5 weeks ago. Offline
Joined: 7 Feb 2010
Posts: 52
Groups: None

Dear,

 

Could I have both the line of balance baseline  and actual progress be shown at the same time?

 

 

 

 

Regards,

 

 

Gary Lo

Ben Taunt
User offline. Last seen 1 year 46 weeks ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Gary Lo,

Yes - on your Line of Balance graph, right-click and chose "Show Standalone".  This opens a new tab within Asta Powerproject with the gantt chart toggled off.  If you now look at Print Preview, you will see that only the LoB graph is included in your print out.

Thanks,

Ben @ Asta Powerproject