Dear colleagues,
I tried to open a project from P6 with Physical % Complete update in Asta Powerproject, but may I know what particular column in Asta that is equivalent to this?
Best regards,
Leonard
Dear colleagues,
I tried to open a project from P6 with Physical % Complete update in Asta Powerproject, but may I know what particular column in Asta that is equivalent to this?
Best regards,
Leonard
Hi Leonard
Try exporting P6 in a diferent location and then opening in Asta.
Alternatively export the % complete data to excell and then just copy paste to Asta.
Best regards
Mike T.
Hi Mike,
Thank you for your response, appreciated that much. But unfortunately as I displayed the Percent Complete column in Asta, it doesn't showing any data. Even the Overall Percent Column is empty as I displayed it. So I still cannot see the data I encoded in Physical % Column in P6 when I opened the project in Asta.
BEst regards,
Leonard
Hi Leonard
Progress > Percent Complete.
Best regards
Mike Testro