Tables

Hello

I'm using v12 and have created a table for a progress report.

How do I copy / import this table into another programme? The table definition doesn't seem to appear in the library explorer....

Any help gratefully received to avoid having to type out all the formula again...

Thanks

Abby

A
Abby Ribbands 👤 Member for 13 years 8 months

Thanks for the help.

I didn't have full functionality in project explorer as it was a programme created in v11 and converted to v12 so I couldn't view the table definition and therefore couldn't copy it.

I've copied the programme into a new v12 file and can now use the table in different projects.

Abby

A
Andrew Pearce 👤 Member for 25 years 1 month

Hi Abby,

When in Library explorer make sure that Table Definition is listed in the Contents of "Project Object"

If not, right click in the Contents area and select show all Libraries, then add Table Definition to the right hand section.

Once you have done this all tables that you have created are visible and can be copied to other projects, good idea to copy into you project template file too.

Hope this helps

Andy

M
Mike Testro 👤 Member for 20 years 7 months

Hi Abby - Welcome to Planning Planet

The columns in Asta are interchangeable with any spreadsheet.

So set up your data table in excell and when you have it how you want it just copy/paste back into a new PowerProject file.

Best regards

Mike Testro

Featured Partner

Top Posters

jeoffrey reyes
15 posts
Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts