User defined field - not showing unless i put a date on the chart

3 replies [Last post]
Christine P
User offline. Last seen 11 years 1 day ago. Offline
Joined: 27 Apr 2009
Posts: 42
Groups: None

Hi there

Made a user defined field via "User Field Manager" called Frequency, all I want to type in there is "Monthly" or "2 yearly" or "Weekly" etc.

I've added it to my chart, I type in the activity description as usual, I type in the "Frequency" column the frequency but when I move off the column onto another, I lose whatever is in the "Frequency" column - unless I draw a date on the gant chart.

I've had this problem before, and Ive sorted it, but that was about 2 year ago and I now cant for the life of me work out how to have whatever is in my user defined columns show up without a dat against it.  Anyone help please!?

Replies

Ben Taunt
User offline. Last seen 1 year 46 weeks ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Christine,

Mike is correct for when your UDF is set up as a Task UDF.  However, if you use a Bar UDF then you should have the functionality you need.

Ben 

Christine P
User offline. Last seen 11 years 1 day ago. Offline
Joined: 27 Apr 2009
Posts: 42
Groups: None

Thanks Mike!

I thought I'd managed it before, perhaps I hadn't after all :D

No worries, Im putting milestones in as I go along anyway and will be moving them all when Im done so the problem is pretty much sorted - for this time anyway :)

Mike Testro
User offline. Last seen 46 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Christine

This is an inherent problem - you can only type data in a user field if there is a task on the bar.

You can put the information in the  Task Name Column - enter a task - Type The Frequency information - delete the task - not the bar - then you can format the text.

I hope that helps

Best regards

Mike Testro