Staff Resource Planning Using ASTA

Hi All,

I have been tasked with creating a site staff resource programme by my employer.

I am relatively new to planning and am hoping someone could provide me with suggestions on how to efficiently create a programme for staff resources using ASTA.

The objective of the programme is to view working time against non productive time to assign excess capacity to jobs.

Any assistance would be greatly appreciated.

Thanks

Joe

M
Mike Testro 👤 Member for 20 years 7 months

Hi Joseph

Set up a series of task hammocks that contain the scope of work for each staff resource. For instance if you are employing an MEP supervisor then add all the MEP tasks to the hammock and then add the Supervisor resource to the hammock.

The same with other trades such as Groundworks - concrete - finishings etc.

Staff that are going to be on site full time add to the project Level 1 summary.

Best regards

Mike Testro

Featured Partner

Top Posters

Zainab El-Beialy
3 posts
Kamlesh Parmessur
4 posts
MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts