Zoom Bar in New Version Asta

3 replies [Last post]
Robert Hughes
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 20 Oct 2006
Posts: 32
Groups: None

I have recently upgraded to the newer version of Asta with the Ribbon rather than the icons and for the most part I am getting on fine with it - however last week my zoom/scale bar at the bottom right corner of the window has disappeared - does anyone have any idea how to get it back?

Replies

Mike Cohen
User offline. Last seen 6 years 39 weeks ago. Offline
Joined: 25 Jan 2019
Posts: 2
Groups: None

I am having this same issue with the disappearance of the status bar.  Can you please tell me how I can turn this feature back on?

Robert Hughes
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 20 Oct 2006
Posts: 32
Groups: None

Thanks for your reply Mike,

I have continued searching and found that the bar I am looking for is called the 'Status Bar' it displays messages at the bottom of the window on the left hand side and then the toggles for Project View, Bar Chart, Histogram, Line of Balance, Properties and the Zoom Slider on the right hand side. The status bar appears in the 'Toolbar Mode' on my computer but not in 'Ribbon Mode'. However on a colleagues computer the Status Bar does appear in Ribbon Mode.

The status bar was there when i first started using ribbon mode but then dissapeared at some point so I must have unintentionally hidden it.

Mike Testro
User offline. Last seen 47 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Robert

I kept the Icons on my version.

I was impressed that when I switched over to Icons my display was just as I left it on v 11.

You can still drag the date scale along and back to change the horizontal scale.

Best regards

Mike Testro