In the latest point release of Asta Powerproject there is a very simple way to achieve the results that you require.
In the columnsheet of Asta Powerproject create two new blank columns then change the properties of these by selecting the tokens for Logic:Predecessors and Logic:Successors. This will indicate to which tasks the task on that bar line are linked to.
If you then go into the Table definition dialogue and scroll across to the right you will find that there are two columns called "Style" and "Details". From the drop downs available you can change the information shown to either task name, task number, WBN number etc and in the details column you can indicate you want full details which will display the link type i.e. FS, FF, SS etc and the amount of lead/lag on that link.
If you then require this to be produced as a printed report you can either simply switch off the bar chart and print the columnsheet on its own from Asta Powerproject or you can copy and paste the information from the columns into Excel or Access as required.
If you are using an older version of Asta Powerproject and you have a current support agreement with Asta you can obtain a CD with the latest version of the Asta Powerproject software from the Asta Help Desk ([email protected]). Please ensure in all correspondence with the Asta Help Desk that you quote your name, company name and the serial number of your copy of the software.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
In the latest point release of Asta Powerproject there is a very simple way to achieve the results that you require.
In the columnsheet of Asta Powerproject create two new blank columns then change the properties of these by selecting the tokens for Logic:Predecessors and Logic:Successors. This will indicate to which tasks the task on that bar line are linked to.
If you then go into the Table definition dialogue and scroll across to the right you will find that there are two columns called "Style" and "Details". From the drop downs available you can change the information shown to either task name, task number, WBN number etc and in the details column you can indicate you want full details which will display the link type i.e. FS, FF, SS etc and the amount of lead/lag on that link.
If you then require this to be produced as a printed report you can either simply switch off the bar chart and print the columnsheet on its own from Asta Powerproject or you can copy and paste the information from the columns into Excel or Access as required.
If you are using an older version of Asta Powerproject and you have a current support agreement with Asta you can obtain a CD with the latest version of the Asta Powerproject software from the Asta Help Desk ([email protected]). Please ensure in all correspondence with the Asta Help Desk that you quote your name, company name and the serial number of your copy of the software.
Michael Gardener
Post Implementation Support Consultant
Asta Development plc.