CONSTRUCTION MANAGER/SITE MANAGER/PLANNER, ABC Building Contracting, Warehouses, housing complexes

START Date: 
March, 2007
END Date: 
August, 2009

 

PROJECTS:

1.       G+M+2 typical floor buildings (3buildings) warehouses (4numbers) and G+1 labor accommodation (1 building) (UAQ)

2.       Office & logistic facility (10 warehouses) on plot no.598-1110 for Grand stores in Dubai investment park Dubai.

Project Engineer, C S L Construction Corporation, Manila, Philippines, Roads and Drainage, Residential Houses, Warehouses, School buildings

START Date: 
September, 1993
END Date: 
December, 1996

 

  • Prepare the overall activity schedule, labor and material schedule.
  • Prepare project cash flow and s-curve.
  • Manage the general coordination of work on site.
  • Review and participate in preparation of variation order requests, and implement accepted variation orders with regards to schedule, manpow