Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Assistant Manager, Frischmann Prabhu (India) Pvt. Ltd, 1.Construction of Multistoried Buildings

START Date: 
March, 1997

1) Degree in Engineering - Direct Final Examination of Sub-Division – II ‘Building & Quantity Surveying’ from Institution of Surveyor New Delhi. (approved by Govt. of India, Ministry of Human Resource Development, Dept. of Education)

2) Diploma in Civil Engineer from K.J..Somaiya Polytechnic Mumbai, Mumbai Technical Board in 1997

Present Experience:

Presently working with Pell Frischmann Limited / Frischmann Prabhu (India) Pvt. Ltd. Mumbai as Assistant Manager Planning.

Preparing project schedule in MS project for all the projects, QS, cash flow

I am directly reporting to Director.

Past Experience:

KEC International Limited, Mumbai as an Assistant Manager-Coordination from June’07 Dec ’10

Responsibilities

Project planning, coordination with site, suppliers, design, client & other functional departments within the organization for 12 projects in 8 counties. Preparation & updation of project schedule, cost planning & MIS updation & Budget preparation.ERP updation. In addition to this also involved in estimation & tendering for all the 8 countries.

Coordinating for the following Projects:

·        Saudi Arabia: 4 projects of 380kV DC OHTL & 1 Project of 132kV DC OHTL

·        Namibia: 350 kV DC OHTL

·        Ethiopia: 230kV DC & 400kV SC OHTL

·        South Africa: 765kV SC OHTL.

·        Peru: Tower supply for 500kV & 220kV lines.

·        Cameron: 225kV line DC OHTL

·        Tunisia: 400/132/33 kV DC OHTL

·        Canada: 500kV double Delta Tower for Zone C design & testing

Was faculty for teaching Project planning & Contract details to new organization jonnies.

Past Experience:

Larsen & Toubro Limited. ECC Division.

Worked with L&T – ECC Division for 4 years as an Sr. Engineer from July ’03 to May’07

Responsibilities:

Planning Engineer for refinery projects & power plants. project planning, monitoring the project progress, budget preparation & monitoring, cash floe project. presenting the progres physical &  financial using MS project & in-house built ERP system.

As Planning Engineer for projects as listed below:

·        Power Plant for Tata Power Corp. Limited, Trombay

·        HPCL Mahul, Mumbai heater modification   

·        PTA Project, Panipat c/o IOCL Refinery  Panipat

·        Ammonia Plant at RCF, Chembur

Was also engaged in construction site activities including civil and mechanical activities for the projects

·        Power Plant for Tata Power Corp. Limited, Trombay

·        HPCL Mahul, Mumbai heater modification   

·        Ammonia Plant at RCF, Chembur

M/s Uttam Engineering Consultancy Pvt. Ltd. Kalyan. Maharashtra      

Was engaged with the organization for almost 2½ years as a Junior Engineer from Jan’01 to June ’03

Responsibilities:

Monitoring site progress, Quality assurance at site, checking & certifying contractor invoices, preparation ofestimates and tenders for buildings, roads & bridges along all CAD Drawings for tender and then working drawings. Fixed the critical alignment of the bridge at Badlapur.

Project executed:

·        MMRDA Transit Tenement camp of 3600 tenements

·        ROB at Badlapur, Maharashtra for KBMC, Maharashtra

·        Railway over bridge at Ulhasnagar for Ulhasnagar Municipal Corporation, Maharashtra

·        B.T. Roads at Bhiwandi for BNCMC, Maharashtra.

M/s. M. Venketrao (Andra Pradesh)

Was engaged with the organization for almost 3 years as a Junior Engineer on site from April’98 to

Dec’00

Responsibilities:

Executing the construction of bridges, planning the daily activities, issuing BBS to bar benders, material reconciliation, finalization of sub contractors, checking their invoices & realizing our payments from Client.

Project executed:

·        2 Bridges on Mumbai–Pune Express Highway at Khopoli.

·        One  PSC Bridge at Thane, Kapurbavdi Junction

M/s. Gammon India Ltd. Prabhadevi, Mumbai

Was engaged with the organization for almost 2 years as a Engineering Assistant on site from

March 97 to March 98

Responsibilities:

Preparation of bar bending schedule, planning & execution of day to day construction activities. Sub contractor invoice checking & certification for further payment.

Project executed:

·        Deo Aqueduct-Narmada Sardar Sarovar Project, Baroda, Gujarat.

·        Reliance Petro-chemicals, Jamnagar, Gujarat.