Project Planner, M.A. Khrafafi and Sons, Kuwait, BAYAN PALACE, PHASE II PROJECT, KUWAIT

START Date: 
July, 1993
END Date: 
February, 1995

BAYAN PALACE, PHASE II PROJECT, KUWAIT. Project is spread over in Bayan area, Kuwait featuring worldclass
interior finishes which also included large area of hard and soft landscaping.
As a Planning Engineer – Responsibilities included Project Planning & Scheduling, Variation evaluation,
Baseline and change monitoring, Review of Payment Applications, Time Extension analysis, Progress reports,
and Progress follow‐ups, cash flow forecast, coordinating subcontractors programme, writing letters