If an early warning/compensation event delays contractor A to the extent that it will delay contractor B is contractor B entitled to a compensation event. If contractor b has not started on site I assume he can not claim an extension to his contract and hence additional costs as his whole contract period has moved as a block
Multiple NEC contracts one project
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Matt
Contractor B would be entitled to an extension of time - shifting the work period to a later date is an EoT.
But then if Contractor A had both contracts then delays on one contract would entitle Contractor A to an EoT on the other.
This is true even if the first delay was not a compensation event.
Best regards
Mike Testro