Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Multiple NEC contracts one project

1 reply [Last post]
Matt Hunt
User offline. Last seen 11 years 29 weeks ago. Offline
Joined: 10 Feb 2010
Posts: 3
Groups: None
If an early warning/compensation event delays contractor A to the extent that it will delay contractor B is contractor B entitled to a compensation event. If contractor b has not started on site I assume he can not claim an extension to his contract and hence additional costs as his whole contract period has moved as a block

Replies

Mike Testro
User offline. Last seen 17 hours 38 min ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Matt

Contractor B would be entitled to an extension of time - shifting the work period to a later date is an EoT.

But then if Contractor A had both contracts then delays on one contract would entitle Contractor A to an EoT on the other.

This is true even if the first delay was not a compensation event.

Best regards

Mike Testro