Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Estimating Structural &Piping Work Manhours

12 replies [Last post]
Mohd Najib Ramlan
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 17 Feb 2012
Posts: 7
Groups: None

Hi..

I'm a fresh graduate planner..and im still learning about planning and scheduling for offshore hook-up and commissioning projects.

I would like to ask about

1. Estimating manhours for structural work such as fabricating, and installing platform deck or pipe support. What basis should I use for the estimation? Is there any books or references for referring the norm?

2. Estimating manhours for piping work such as fabricating, installing and tie-in. What reference should I use to estimate the manhours.

 

I appreciate to all that can give me a lessons about my humble questions. Thank you very much.

Replies

dendy efendi
User offline. Last seen 8 years 4 weeks ago. Offline
Joined: 28 Oct 2016
Posts: 2

to estimate man hour piping you need more time experience , need investagation to gain some information from welding man power supply subcontractor. Because experience completeing piping fabrication time difference each place and condition.

Rashid Iqbal
User offline. Last seen 2 years 17 weeks ago. Offline
Joined: 7 Apr 2010
Posts: 70

Mohd Najib,

Everyone was 'new' someday and so don't worry thinking that your questions are silly. I will try to guide you a bit.

1. Schedule baseline will be loaded for the budgeted hrs (hrs included in the estimate)

2. Open the estiamte and you will see piping take off; it will show you the ISO's and the budgeted hrs.

3. I think that you will be scheduling at a FIWP level. This means you have to map the estimated hrs by FIWP.

4. Once you get to this level then we can talk about Rules of Credit etc.

 

Regards

Rashid

christian oz ibekwe
User offline. Last seen 8 years 43 weeks ago. Offline
Joined: 29 Apr 2015
Posts: 2
Groups: None

How can one estimate the hours for installatio of structural members for offshore installation . this includes pipe hangers

John Kuypers
User offline. Last seen 10 years 33 weeks ago. Offline
Joined: 21 Feb 2012
Posts: 3
Groups: None

Guys, Have a look at www.costeng.com their software tools provide automatic access to substantial manhour databases for spooling of pipework in a workshop and installation of spooled and site run pipework

Bernard Ertl
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757

I realize that your original request was posted a few months ago, but in case you are still looking for resources, our eTaskMaker system includes estimating modules for piping demolition, fabrication and erection.  You can estimate (prepare manpower loaded execution schedules actually) piping work based off of engineering isometric diagrams.

Mohd Najib Ramlan
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 17 Feb 2012
Posts: 7
Groups: None

Oo..thanks guy..now i got it... So what is the Spon's books norm were used for?.. I noticed that the unit they used in the table such as meter, numbers, etc.. So..what actually the norm were applicable for in the fabrication..

Sorry to ask such a silly question as this..but I really don't know about it...

Thanks for helping..

Anning Sofi
User offline. Last seen 6 years 17 weeks ago. Offline
Joined: 22 Jan 2012
Posts: 89
Groups: None

Let us take your example:

Fabrication works, your reference is the Isometric drawing of 12 m pipe of 24" schedule 80 with 10 weld joint.

Can you identify what related tasks in the "Spons" book is applicable for estimating the manhours?

Also, the production rates in this book may not be applicable to your organisation productivity in the field? Do the operatives have the same skill? If not, what factor are you going to use? How about methods? Logistics? Materials? Equipment?

Suppose, there is no "Spons" book? How?

 

A planner with related experience can at least identify what tasks are needed for fabrication works of the pipe mentioned in your example.

As Mike has mentioned, speak to those people who are in the know.

 

 

Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422

Mohd,

For piping: You must learn the so-called units: inch-dia and / or inch-meter

For structural steel: Tons and / or kilograms

It is really the experience that figure it out. 

Mike Testro
User offline. Last seen 49 min 10 sec ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Mohd

Experience is essential for a planner - if you can't build it you can't plan it - otherwise you are a scheduler working on someone elses plan.

The "Spons" books are a guide only - do not take the data as being relevant to your project as there are so many variables.

As I said earlier you need to go back to the estimated cost plan and speak to your estimator.

Best regards

Mike Testro

Mohd Najib Ramlan
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 17 Feb 2012
Posts: 7
Groups: None

Thanks for the comments. So, that's mean, planning is all about base on experiences only?..no specific reference are applicable?

I'm not really in estimating on whole projects. I had been assigned to understand how to estimate manhours by using standard norm. One of their suggestion is by using "Spon's Fabrication Norm for Offshore Structures" book for starting points.

Let say I have an Isometric drawing of 12 m pipe of 24" schedule 80 with 10 weld joint. How do you guys really estimate the manhours of this work?

Thanks for your idea guys. Really appreciate it as im lack of the experience.

Anning Sofi
User offline. Last seen 6 years 17 weeks ago. Offline
Joined: 22 Jan 2012
Posts: 89
Groups: None

i find it iirregular that a fresh graduate is tasked with estimating manhours for offshore hook up and commissioning projects. Manhour Estimation needs a degree of experience and understaning of the tasks, operations involved, manpower and equipment, crew size and durations.

 

The estimated manhours for structural and piping should already be available by the estimating department, or by the department who prepared the technical or commercial proposals in securing the contract. Inquire from them.

Mike Testro
User offline. Last seen 49 min 10 sec ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Mohd

Your sole source for productivity in any project has to be the BoQ or cost plan.

The estimator will have split the unit prices into Labour Plant and Materials.

You must study the Labour and Plant content to ascertain the productivity for that specific project.

Best regards

Mike Testro