Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Earn value

3 replies [Last post]
Azvi Hanifa
User offline. Last seen 18 years 43 weeks ago. Offline
Joined: 15 Sep 2004
Posts: 14
Groups: GPC Qatar
Presently I’m working with project management team for the as a planning engineer.

The cost of the project is one Billion US$, So far I have intensively involved in the progress that is site evaluating, monitoring and reporting. Project’s construction program being resources and cost loaded. Recently our client interested to measure the earn value through the P3, I have not so much idea how? what ? sort of reports to be produced, in oder to present time and cost impact reports.

Please provide some advise with examples.
E-mail- azvips@hotmail.com

Your prompt reply would be much help full.

Thank you very much.

MHM. Azvi

Replies

Alex Wong
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Azvi

One of the most important pre-requisite to run a EV report in P3 is to have your schedule loaded with resources.

If the project is still in its early stage, it will be very easy to setup, otherwise you will need a lot of effort to report EV in your schedule.

In addition, in order to track back the progress already made in past reporting period. You have to rebuild your schedule with each individual month schedule and save each period performance. If you are not ploting the EV curve in P3 with period performance saved, you will need your client agreed to run the EV report outside P3. Otherwise what is in the EV report will be different to your current P3 schedule.

Types of reports that you can produce in P3 is EV S-Curve, (Using Layout) EV period table report.

Furthermore, there is a few tricks that you need to be aware of in P3 if you recording Actuals and have Target project in your existing P3 schedule. It will give you a wrong EV report if you are not careful with Budget, Remaining, actuals and Target Project.

Regards

Alex
Paul Harris
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
You will find an article on my web site titled Practical Application of Earned Value under Technical Papers.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au
Jaco Stadler
User offline. Last seen 18 years 6 weeks ago. Offline
Joined: 8 Sep 2004
Posts: 299
Groups: None
Are you working for Qatar Petroluem