Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Percentage complete or remaining duration

8 replies [Last post]
Forum Guest
User offline. Last seen 17 weeks 5 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
As someone from the ’old school’ I find it somewhat annoying that there is an increasing bias towards using percentage complete when updating plans.

My argument is simply that % complete can bare no relationship to remaining duration and consequently makes the plan incorrect(and subsequently cost to completion.)

I also think that it is somewhat illogical to allow completed (or uncompleted) activities after (or before) Time-now although I have seen many, many instances where plans are shown thus.

Am I missing something here - What do you lot think?

John

Replies

Forum Guest
User offline. Last seen 17 weeks 5 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Hi Bernard,
well you wont belive it but i have just figure out the same answer with a few repetative examples. the process can safely be used if the duration remains the same i.e. baseline Vs Actual. but this is not the case in reality as some durations vary. luckily, i have found an M&E schedule for the exact same date i.e. my selected data date but civil works has to be estimated.
any solid ideas about its measurement.. or is it ok for such analysis...
Regards.
hamish
Bernard Ertl
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757
Hi Hamish,

That assumes two things:

1. The physical progress (effort/manhours) is linear with time.
2. The progress was in line with the estimate (ie. there were no problems in the field and the original estimate was good).

Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
Forum Guest
User offline. Last seen 17 weeks 5 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Hi,
I am working on a delay calim and made a programme, a replica of the actual project programme and now i am progressing it. in the past i did the same exercise with subcontractor’s programmes and it worked out pretty similar to what their own plan said (Made using a different planning software). i used percentage complete to update the progressed schedule and because it was planned similarly, so the results were accurate too.
Now i think another point is worth discussing here, which i used before. i have selected a data date and the activites that were not complete and were in progress (Due to lack of progress data for this particular data date), i am using the task completion date and percentage complete.
an example being:
Percentage COmplete=(Duration to date)* 100/Task Act. Duration
What u think??
Cheers.
Hamish
Zq qz
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
Strongly aggree with Bernard. There are many ways in handling it. and also depend what is your assesment.
I agree that % complete is rather strange factor. It may be different for amount (volumes) of work, duration, cost, material consumption. So we just don’t use it at all. It makes no sense.
Bernard Ertl
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757
Obviously, % complete in terms of effort (manhours) does have a bearing on remaining duration. It’s just that it may not have a linear relationship.

The more detailed your plan (and thus the smaller overall durations/manhours assigned to any given task), the less significant the non-linear distribution of manhours across duration for a given task will be.

Our system allows updating % complete in effort (manhours) and duration (time) separately if desired. Some systems allow you to specify the manhour/time distribution ratio (front loaded, end loaded, etc.) and calculate time/manhours based upon that formula. There are many ways to handle it.

Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
Forum Guest
User offline. Last seen 17 weeks 5 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Good point! - the end result is obviously time - but would probably reflect effort given to an activity.
Bernard Ertl
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757
% complete in terms of effort (manhours), time or cost? What are you referring to specifically?