I successfully export P6 files to excel,but when I importing back excel to p6 after I load resources,BOQ,cost either the program said out of memory or not responding.I have 25,000 activities in the Project. Your help will be highly appreciated.

Replies

Daniel Limson
User offline. Last seen 5 years 4 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Hi Jaime,

Try doing it in batches, the file must be too big. Note that when importing back to P6, you need the same file or source, when you export to P6, there are actually 2 worksheets created.

Best regards,