Changing Activity type for 3000+ Activities

1 reply [Last post]
John Maiurano
User offline. Last seen 12 years 19 weeks ago. Offline
Joined: 15 Mar 2012
Posts: 3
Groups: None

What is the fastest way to change over 3000 activities from resource dependent to task dependent? P6 V8.1

Thanks

Replies

usman arshad
User offline. Last seen 5 years 24 weeks ago. Offline
Joined: 19 Dec 2010
Posts: 10
Groups: None

John

1- u can do it through global change

2-u can add one column for Activity type and then change one activity type manually and crtl select other acitivites and press crt+E. this is like in excel we have crtl+d option.