Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Changing Activity type for 3000+ Activities

1 reply [Last post]
John Maiurano
User offline. Last seen 12 years 34 weeks ago. Offline
Joined: 15 Mar 2012
Posts: 3
Groups: None

What is the fastest way to change over 3000 activities from resource dependent to task dependent? P6 V8.1

Thanks

Replies

usman arshad
User offline. Last seen 5 years 39 weeks ago. Offline
Joined: 19 Dec 2010
Posts: 10
Groups: None

John

1- u can do it through global change

2-u can add one column for Activity type and then change one activity type manually and crtl select other acitivites and press crt+E. this is like in excel we have crtl+d option.