Changing Activity type for 3000+ Activities

2 replies [Last post]
John Maiurano
User offline. Last seen 12 years 19 weeks ago. Offline
Joined: 15 Mar 2012
Posts: 3
Groups: None

What is the fastest way to change over 3000 activities from resource dependent to task dependent? P6 V8.1

Thanks

Replies

muhammad haziq
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 24 Jun 2009
Posts: 3

the other easy way to change the multiple activity type is..

add another column into your p6 layout>add "activity type" column this code can be found under general category>change the first activity from "resource dependant" to "task dependant">select all the activity you want to change>right click and click fill down.

for code type changing i usually use the fill down function because it much more easier and faster. hope this help

 

Vaughn Edwards
User offline. Last seen 10 years 28 weeks ago. Offline
Joined: 1 May 2008
Posts: 16

Perform a global. 

Where - Activity Type Equals Resource dependent

Then Activity Type Equals Task dependent

Click Change