Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

External Late Finish as a Constraint

2 replies [Last post]
DATTATREYA PADHARTHI
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 18 Apr 2003
Posts: 90

Hi Planners,

Wish you all a happy and prosperous new year!

We have copied multiple projects across to a  different EPS node have links across Projects.

After Scheduling the new set of projects, we see negative floats of nearly 1500 days, bit of investigation shows constraint on some of the activities as External Late finish.

Has anyone come across this issue.

Regards

Datta

Replies

Jose Frade
User offline. Last seen 3 years 24 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None

Hello DATTATREYA

Basically the previous answer relates exactly what happened. Now one quick way to clean all those external constraints.

Make a filter or a sort on that field and isolate all the activities concerned. then clean the first constraint and selecting also all the others make a "fill down" - this clears all the data in that particular field and activities as you know. Note that you should only clean the information after ensuring all your activities have included in the project file you pocess all the necessary predecessors and successors, otherwise you will have your activities moved to the earliest possible date (and that can be the data date).

Hope it helps.

 

Have a nice 2012

JMFrade

 

Hatem Hejazi
User offline. Last seen 29 weeks 6 days ago. Offline
Joined: 30 Aug 2008
Posts: 11
Groups: GPC Qatar

The external start or finish dates are the dates the external relationship was scheduled to start or finish. This may be used to calculate the start date or finish date of the current activity during scheduling. 

This field is populated when the project is imported and when an external relationship is lost.An external relationship may be a relationship with an activity that does not exist in the present database. So if you received this schedule from someone else and they had a link to activities in other projects on their computer but they did not give these projects as an xer file then the external start or external finish box would be populated during importing.

Also if you press F9 and then select the options button and look under the General tab and look at the top box to see if ignore relationships from other projects is checked or unchecked that would be the difference you mentioned

Answer by: Zoltan Palffy, www.pmsite.com