Flaws in P6 – Setting an ongoing program as Baseline

Dear All,

Why P6 can’t shows correct dates of Start and Finish (BL Start & BL Finish), if we set an ongoing program as baseline program. When we insert baseline column of an ongoing program, most of the activities, which are already completed are showing different dates. The problem can be solved by inserting a column called BL Actual start and BL Actual Finish. But when we insert these two columns, the forthcoming activities cannot be seen? How to solve this problem.

regards,

 

Haresh Jayanth - PMP , PSP

Forum Sponsor

Top Posters

GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts