P6 Calendar - modify work hours

I
Ife Olyke 👤 Member for 19 years 4 months

Hi Planners,

I have an activity (let’s say its activity ‘A’) within my P6 plan that will take 6 hours to complete and has a fixed start date and time. In carrying out this task, no other activity can be progressed. I need to make this visible in the P6 plan by setting the work hours for activity ‘A’ on the day as ‘Nonwork ‘. Alternatively, I could set the whole day, but that will portray a false impact on the schedule duration.

Who has got an idea? Thanks

 

olyke

Forum Sponsor

Top Posters

AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts