Start Date Problem with Finish to Start Relationship

1 reply [Last post]
Robert McGhee
User offline. Last seen 8 years 50 weeks ago. Offline
Joined: 27 Mar 2008
Posts: 15
Groups: None
I have a predecessor activity 65% complete with a finish date of September 13, but the successor activity with a finish-to start relationship shows a start date of September 13 after I "schedule". Each has a "physical" percent complete type and there are no lags in the relationship. Never had this happen before so am looking for some insight.

Thanks,
Robert McGhee

Replies

Shareef Abdul Azeez
User offline. Last seen 3 years 22 weeks ago. Offline
Joined: 19 Sep 2005
Posts: 183
Hi Robert

Check the time format...

Include minutes and check ....!!!