Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Start Date Problem with Finish to Start Relationship

1 reply [Last post]
Robert McGhee
User offline. Last seen 8 years 35 weeks ago. Offline
Joined: 27 Mar 2008
Posts: 15
Groups: None
I have a predecessor activity 65% complete with a finish date of September 13, but the successor activity with a finish-to start relationship shows a start date of September 13 after I "schedule". Each has a "physical" percent complete type and there are no lags in the relationship. Never had this happen before so am looking for some insight.

Thanks,
Robert McGhee

Replies

Shareef Abdul Azeez
User offline. Last seen 3 years 7 weeks ago. Offline
Joined: 19 Sep 2005
Posts: 183
Hi Robert

Check the time format...

Include minutes and check ....!!!