Global Change Implementation on "Finish Date Column"

1 reply [Last post]
Izam Zakaria
User offline. Last seen 7 years 36 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Guys,

I’m just wonder if we can do global change on "finish date column"

What I did, I imported the excel data onto user_end_date(my forecast date) I want to use global change something like this:

If user_end_date bigger than XXX
Then Finish date = user_end_date

but the problem is I didn’t find "finish date" column instead planned finish date.

so is it we can’t change the finish date automatically?

thx

Replies

Rodel Marasigan
User offline. Last seen 11 weeks 20 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Izam,
Finish date field is a result of current early dates which is not updatable. If you need to update finish date using Global change uses Remaining Early Finish date which is equal to Finish date.