FS RELATIONSHIP Confusing

1 reply [Last post]
kumar s
User offline. Last seen 8 years 34 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159
Dear guys, i was refering to the last years project. in the primary baseline bar plan.but there are some relationships which i cannot understand. for ex i have A and B activities which has FS relationship between them. there is no lag. the A activity has FS to some other activity also C . BUT IN THE SCHEDULE THE B activity is starting before the A activity has finished. why is this happening. please clear my doubt..... thanx...

Replies

Rodel Marasigan
User offline. Last seen 11 weeks 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Kumar,
It either have mandatory constraints or Act is finished but data date is lower than Act start and finish date.