Baseline Assigned Slip Away

1 reply [Last post]
Izam Zakaria
User offline. Last seen 7 years 36 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Gents,

I’ve updated schedule and now I make it as baseline to the new schedule.

But the problem is some of baseline plan date slipped from the original and i realized it was the completed one(100%) for instance it’s completed on Apr but the date now extended to June.

Why this thing happen?

Replies

Rodel Marasigan
User offline. Last seen 11 weeks 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Izam,
Baseline use planned date and not actual date. If you wanted to show actual date, link below thread where I explain how to use actual date on baseline.
How to set baseline after the revised schedule Post #2