Weight factor

3 replies [Last post]
SARAV VENKAT
User offline. Last seen 31 weeks 4 days ago. Offline
Joined: 12 Jan 2010
Posts: 6
Dear All,

My Consultant want to load weight factor in baseline schedule. I have loaded cost and manpower. Is there any option in Primavera calculate weight factor as per loaded cost and manpower instead of manual entry.

venkat

Replies

Izam Zakaria
User offline. Last seen 7 years 36 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Do uploading data onto excel spreadsheet first then further import to P6
Barry Fullarton
User offline. Last seen 15 weeks 17 hours ago. Offline
Joined: 6 Jan 2009
Posts: 44
Groups: None
hi

i want to load as follows

Design 10%
procurment 15 %
etc

how do i ensure that these activities below this remain as fixed

Rodel Marasigan
User offline. Last seen 11 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Hi Vencat,
Yes, you can use export/import to excel facility to load your cost and resource. Use resource assignment option.