In the windows toolset their are only two nice-to-have extras.
A project specific roll-up calendar for durations. Not the fix we really needed ( which would have been "Elapsed days" as in MSP 2007) but desparately needed
The ability to copy baselines in place - also badly needed as updating baselines remains fraught.