Upgrade from 6.2 to 6.7

1 reply [Last post]
Sophia M
User offline. Last seen 14 years 19 weeks ago. Offline
Joined: 10 Mar 2010
Posts: 10
Groups: None
Does anyone know how much the upgrade costs....what is the advantage of 6.7 versus 6.2?

Replies

David Kelly
User offline. Last seen 2 years 2 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
In the windows toolset their are only two nice-to-have extras.

A project specific roll-up calendar for durations. Not the fix we really needed ( which would have been "Elapsed days" as in MSP 2007) but desparately needed

The ability to copy baselines in place - also badly needed as updating baselines remains fraught.

In the web toolset there are to many nice shiny new toys to list here!