Est Weight

7 replies [Last post]
Kumar J
User offline. Last seen 5 years 50 weeks ago. Offline
Joined: 24 Jun 2001
Posts: 21
Dear Friend,

Can anyone guide how to use Est Weight column in P6.

1. What is the use of it?
2. How to use it?
3. Whether S Curve can be generated for early & late dates?

Regards,

Bharath Kumar J

Replies

Siddic K
User offline. Last seen 9 years 22 weeks ago. Offline
Joined: 11 Oct 2011
Posts: 6
Groups: None

Hi ,

How to calculate the resources in tentative stage and how to apply in P6. 

Please anybody help me with some example....

 

 

 

 

Thanks 

Siddic K

Khuong Do
User offline. Last seen 15 years 3 weeks ago. Offline
Joined: 22 May 2009
Posts: 27
Groups: None
Hi.
That’s right, you have to key in Est weight for each activity base on your experience.
Then run Top down estimation in Tool menu.
Kumar J
User offline. Last seen 5 years 50 weeks ago. Offline
Joined: 24 Jun 2001
Posts: 21
Dear Sir,

Whether i will have manually key in all est weight values against each activity?

If i need to enter manually, then, i will check for S Curve as suggested by you.

Regards,
Khuong Do
User offline. Last seen 15 years 3 weeks ago. Offline
Joined: 22 May 2009
Posts: 27
Groups: None
You can choose S-curve to display base on early or late date by setting option in Edit -> User Preference -> Resource Analysis.
Khuong Do
User offline. Last seen 15 years 3 weeks ago. Offline
Joined: 22 May 2009
Posts: 27
Groups: None
You can choose S-curve to display base on early or late date by setting option in Edit -> User Preference -> Resource Analysis.
Khuong Do
User offline. Last seen 15 years 3 weeks ago. Offline
Joined: 22 May 2009
Posts: 27
Groups: None
Hi Bharath
Est weight is used for Unit Top-down estimation. Let say you have 1000 unit, base on activity’s Est weight Primavera will deliver units to each activity.
Kumar J
User offline. Last seen 5 years 50 weeks ago. Offline
Joined: 24 Jun 2001
Posts: 21
Can anyone guide the use of Est Weight in Primavera P6.

Regards,
Kumar