Importing P5 project into Contractor 6.1 problems

1 reply [Last post]
mike fenton
User offline. Last seen 15 years 37 weeks ago. Offline
Joined: 26 Jun 2008
Posts: 5
When I import a P5 project (xer) into Contractor 6.1, the budgeted total costs are modified. They should be the same values. There are no other problems, eg: activities, logic, durations are all correct. It seems to be only the budgets that are an issue. Has anyone had this problem and worked out a solution?

Replies

mike fenton
User offline. Last seen 15 years 37 weeks ago. Offline
Joined: 26 Jun 2008
Posts: 5
Problem solved!!!!
The project I was importing had a currency based in Australian dollars and the project I was importing into was based on US Dollars. This currency exchange was set to 1.7964 so my original project of say a budget - $100M was showing up as $55M when imported.