How to find Relationship ID

3 replies [Last post]
Ian Mackrell
User offline. Last seen 10 years 31 weeks ago. Offline
Joined: 15 Jul 2008
Posts: 27
I am currently comparing programmes using Claim Digger and i am upto the relationship lags, however it only states the relationship ID number not the Activity ID. How do i find this id in the programme?

Cheers

Ian

Replies

Ian Mackrell
User offline. Last seen 10 years 31 weeks ago. Offline
Joined: 15 Jul 2008
Posts: 27
Thanks Barrie,

However, i cannot find the activity ID. I have run with the task_pred_id with the proj_id (shrt_name (filtered to the relevant project)), but for life of me cannot link it with the act_id (shrt_name) as it returns to null.

I would be grateful if you knew how to get this.

Cheers mate
Barrie Callender
User offline. Last seen 1 year 14 weeks ago. Offline
Joined: 15 Feb 2006
Posts: 39
Groups: None
I don’t believe you can see the "Relationship ID" from Claim Digger displayed in P5.

You need to go to the database and run a SQL query to get to it. It is the task_pred_id column in the taskpred table. It is unique in the database.
Ian Mackrell
User offline. Last seen 10 years 31 weeks ago. Offline
Joined: 15 Jul 2008
Posts: 27
In P5!!!!!