Graphs & S Curves

1 reply [Last post]
shiv rao
User offline. Last seen 12 years 2 weeks ago. Offline
Joined: 10 Mar 2008
Posts: 62
Hi to All,

What are the best S curves drawn from Primavera.

Please send some samples at jayshiv26@hotmail.com.

Also if we want to change Globally the man hrs for one particular resource with a factor of 0.9.
How can that be done?

Regards

Shiv Rao

Replies

David Podmore
User offline. Last seen 12 years 32 weeks ago. Offline
Joined: 26 Apr 2006
Posts: 74
Groups: None
Shiv,

To do a global change....

(1) In "Select Subject Area" choose "Activity Resource Assignments"
(2)Where - Resource ID Name = (your target resource)
Then - Budget Labour Units = Budget Labour Units x 0.9

Check the result is what you expected and commit.

David