Scheduled % complete v/s Activity % complete curve

A
Abdullah Merchant 👤 Member for 15 years 7 months

Hi,

I am relatively new to planning, and I am currently working on a Project(Clients Side) where I have not loaded any resources. I am currently using MS Project 2007 adn would like to know how to get and S Curve in excell.

Also, I have notice that the baseline dates in MS Project can be chnaged from the column,unlike P6. Is this so or am i missing something here.

N
niles luo 👤 Member for 20 years 7 months

Hi,

I think in this situation PM can not direct show this S curve.Maybe PM can,but I do not know.

My suggestion is

1,Create a resource named A, labor or nonlabor is ok

2,Assign resource A to every activity. The Unit use the default value is ok.

3,Then use the Resource Usage Profile, we can see the Unit Cumulative Curve of resource A. The numuber/total unit is the percent complete.

Maybe above is not a good idea, only FYI.

N
niles luo 👤 Member for 20 years 7 months

Hi:

Pls give the further information about:

1,Do you want to show the S curve in PM or the other system just like MS Excel?

2,Do you assign resources to the activities?

Forum Sponsor

Top Posters

James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts