Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Acitvity Sequence in WBS

4 replies [Last post]
Minhas Shaikh
User offline. Last seen 13 years 35 weeks ago. Offline
Joined: 30 Mar 2007
Posts: 44
Hi,
I am trying to copy of one WBS including atvities in same project but after past the order of activities is changed. I need those activities in same order.
Can anyoby help me for solving this problem. The are 26 activities in that WBS all are linked.

Thanks
Minhas

Replies

Suresh Sankaranku...
User offline. Last seen 5 years 10 weeks ago. Offline
Joined: 30 Jul 2006
Posts: 77
There is no big deal on this issue.Your question is self explanatory that, you are using Acitivity id as sorting field. So nothing to do but just click on the activity id Titile until you see a watermark of a small arrow pointing down.

Good Luck
Suresh
Niek Zonneveld
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
Minhas,

Patricia is right. P5 uses a FIFO buffer, so the order in which you copy is the order in which you paste.

H.T.H.
Patricia Le Clainche
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 18 May 2007
Posts: 86
Groups: None
Hello Minhas,
Regarding the order you want after copying, on which column do do sort ? By Activity ID? By Start or Finish Date ?
If you want to sort by Activity ID, you should be able, just after copying to change Activity ID in order to sort the good way.

Good luck.
Patricia

Karim Mounir
User offline. Last seen 10 years 10 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Hi Minhas,

Each activity in a schedule has its unique "Activity ID".

If you want to show the activities in the new WBS sorted as in the old WBS, then u’ve to link the 1st activity in the new WBS with a predecessor in the old WBS (or assign a constarinat date to it) and since the activities in the new WBS are linked then after setting the data date and scheduling the programme the start/finsh dates will be updated, u can sort them by start date (By clicking on the column titled Start).

HTH

Regards,