Baseline Variances

2 replies [Last post]
Rob Mezger
User offline. Last seen 13 years 12 weeks ago. Offline
Joined: 5 Feb 2007
Posts: 4
Groups: None
I am working in P5 and have been exploring varainces to baselines. I have a good understanding of how baselines work and I understand that P5 calculates variances to baselines using the early start and finsh dates. Does anyone know if it is possible to calaculate the variances based on the late start & late finsh dates instead?

Replies

Rob Mezger
User offline. Last seen 13 years 12 weeks ago. Offline
Joined: 5 Feb 2007
Posts: 4
Groups: None
Thanks for the info Dieter - much appreciated,

Rob
Dieter Wambach
User offline. Last seen 7 years 17 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Rob
There is no direct way.

You can use a workaround - not elegant, but it works. Before you create a BL you move the late dates into UDF (User Defined Fields). Later you can compare with a global change and two more UDF.
Ask your dealer to force Primavera to include the comparison of late BL dates into the standard.
Regards
Dieter