Start with some general question to understand your problem a bit deeper.
1 . Please confirm your versionis is P3e 3.5 ??
2. Did you install all the patches??
If you have installed all the patches then my suggestion is that:
Then what might be causing the recurring logic is activites between projects are interlink with a mess.
In order to have a clear interfaced project plan you might have to delete all the existing interproject relationship and replace with a series of start and finsih milestone.
As a result, all activities linkage will be very clear and it will solve your problem ofo recurring logic (Loop)
RE: P3.5E Loop Error while scheduling multiple projects
Dave
Start with some general question to understand your problem a bit deeper.
1 . Please confirm your versionis is P3e 3.5 ??
2. Did you install all the patches??
If you have installed all the patches then my suggestion is that:
Then what might be causing the recurring logic is activites between projects are interlink with a mess.
In order to have a clear interfaced project plan you might have to delete all the existing interproject relationship and replace with a series of start and finsih milestone.
As a result, all activities linkage will be very clear and it will solve your problem ofo recurring logic (Loop)
HTH
Alex