Project Levelling

1 reply [Last post]
Paula Walsh
User offline. Last seen 18 years 1 week ago. Offline
Joined: 8 Jun 2006
Posts: 13
Groups: None
When using the leveling tool in Primavera (release 5.0) there is a significant difference in the project end date and activity task start and finish dates when the "preserve schedule early and late dates" option is selected.

How do I know to utilize this option or not, it prolongs the project by 2 months, but when the option is not chosen the project ends earlier. There is not an over allocation of resources that I can see when the option is not selected, but I do not understand what the program is doing differently when the option is selected or not.


Paula

Replies

David Kelly
User offline. Last seen 2 years 2 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Paula,

58 views of yout post and no reply!! Couldn’t resist the challenge. Need to know more about what dates you are actually looking at. If you group and sort by Project so that dates role up to the project level, what are Finish, Early Finish and Remaining early Finish, with or without "preserve"