Relationship has been changed automatically!!!

1 reply [Last post]
Amir Dadbakhsh
User offline. Last seen 4 years 1 week ago. Offline
Joined: 13 Oct 2004
Posts: 42
Dear Planner
I’ve faced very strange thing!!!, and I hope anyone knows its reason and gives its solution to solve that.
Imagine a project with following activity:


Activity………Successor………Predecessor
a…………………………………bFS………………………………
b…………………………………aFS………………………………
c…………………………………………………………………………


Activity………Successor………Predecessor
a…………………………………………………………………………
b…………………………………………………………………cFS
c…………………………………bFS…………………………………

When I close mentioned project and open it again (even when I close P3e and open it again) activity relationships have been changed!!!


Activity………Successor………Predecessor
a…………………………………aFS…………………………………
b…………………………………………………………cFS , aFS
c…………………………………cFS…………………………………

To solve mentioned problem even I used "purge deletes" but they couldn’t help me to solve that.

My program situation is:
1) Primavera 5, SQL
2) I’ve marked "Purge deletes when existing project management" in "admin preference"
3) Added "UseSPToPasteProject=0" to "pm.ini" to solve "loosing UDF data"

Thanks in advance
Amir Dadbakhsh

Replies

Amir Dadbakhsh
User offline. Last seen 4 years 1 week ago. Offline
Joined: 13 Oct 2004
Posts: 42
Adding "UseSPToPasteProject=0" caused this problem. When I delete that from "pm.ini", activity relationship came right.
So I guess other planner to prevent loosing UDF data and prevent activity relationship changing, just organize the project screen by something other than EPS (as mentioned by Bill McMichael in "UDF - Loosing data" topic).

Amir