Duration% Complete X Units % Complete
Forum Sponsor
Top Posters
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Kevin,
Thanks for your interest.
Best regards.
Marcio Eduardo
Rio de Janeiro - Brazil.
Marcio
It certainly is possible (and often necessary) to have Duration % and Units % working independently. In project view, select the Calculations tab and make sure the box titled "Recalculate Actual Units and Cost when duration % complete changes" is NOT ticked.
You will still need to define a suitable default % complete type for your activities (either duration, units or physical) but you can display the columns for each of these % types in the activity view.
Regards