Displaying Duration In Phase Title Bar

On my project I have all the activities organized by phase.  Is there a way to automatically display the total duration of the phase in the title?  

 

For example, if I had a phase 1A, and all the activites in phase 1A would take 30 days to complete, it would display '30' days next to where it says phase 1A.

 

Thanks in advance.

K
Kaif Mohsin 👤 Member for 15 years 4 months

Dear Jones,

Yes, there is. If you are using Primavera P6 than go to the "View Menu" then to "Group and Sort" and then under the "Display Options" Tab , tick the "Show Group Totals" option and press "Ok"

Kaif...