Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Create an S-Curve based on Sched % Comp in P3 v3.1?

2 replies [Last post]
John Rogers
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 19 Dec 2003
Posts: 4
Groups: None
Dear all,

I would very much appreciate some help...

I am trying to produce an S-Curve based on Schedule % Complete, based against by target programme. Both programmes are resource loaded.

Many Thanks

Regards,

John R

Replies

John Rogers
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 19 Dec 2003
Posts: 4
Groups: None
Excellent, thanks very much for your help Samer. Much appeciated.

Regards,

John R
Samer Zawaydeh
User offline. Last seen 5 years 31 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear John,

Go to Display screen,
Select
Type = cost
Timer Interval = Months
Remove check from Histogram
Select Total from "Resource Profile/ table"

Then you can select what you want to see for each resource or for all.

Best,

Samer