Create an S-Curve based on Sched % Comp in P3 v3.1?

2 replies [Last post]
John Rogers
User offline. Last seen 2 years 7 weeks ago. Offline
Joined: 19 Dec 2003
Posts: 4
Groups: None
Dear all,

I would very much appreciate some help...

I am trying to produce an S-Curve based on Schedule % Complete, based against by target programme. Both programmes are resource loaded.

Many Thanks

Regards,

John R

Replies

John Rogers
User offline. Last seen 2 years 7 weeks ago. Offline
Joined: 19 Dec 2003
Posts: 4
Groups: None
Excellent, thanks very much for your help Samer. Much appeciated.

Regards,

John R
Samer Zawaydeh
User offline. Last seen 5 years 39 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear John,

Go to Display screen,
Select
Type = cost
Timer Interval = Months
Remove check from Histogram
Select Total from "Resource Profile/ table"

Then you can select what you want to see for each resource or for all.

Best,

Samer