Cannot get restraint to stay

1 reply [Last post]
Greg Swartz
User offline. Last seen 16 years 24 weeks ago. Offline
Joined: 26 Jul 2007
Posts: 6
Groups: None
I have an activity that is started, and by the OD and the RD, the task should have an early finish of about 15 March. The calculation keeps placing back to 25 Feb. No successors are starting or finishing prior to that date. The predecessor finished 4 Jan. Why will P3 not accept an early constraint for a finish for the 15 march?

Replies

Mangesh Khuspe
User offline. Last seen 44 weeks 4 days ago. Offline
Joined: 10 Apr 2007
Posts: 162
Hi
i suppose the activity has started and u have updated it,
hence it will take constraint.

cheers
mangesh