Copy and Pasteing From P3 to Blank P3 project

A
amit amit 👤 Member for 19 years 10 months
A
amit amit 👤 Member for 19 years 10 months

Thank you all for your help. I have managed to copy the P3 file.

A
Ashraf Jahangeer 👤 Member for 19 years 1 month

Hi Amit/Anoon



Similarly there is a transfer layout facility.





Regards,





Ashraf



PS :Also check that you are copying All activities and not a particular fiter.

A
Anoon Iimos 👤 Member for 19 years 9 months

i believe there is a transfer function for the activity codes, try it

A
A D 👤 Member for 19 years 1 month

HI AMIT,



if u r copying existing project, then use copy tool.



Go to Tools --> Project Utilities --> Copy

and then in the open window, type the new project name in the project group tab and not project name.



All layouts and filter will be copied.



Hope this is what u have asked for.



Cheers,



Raviraj

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts