Update Progress P3 3.1

4 replies [Last post]
PAUL WATER
User offline. Last seen 17 years 1 week ago. Offline
Joined: 6 Jun 2007
Posts: 18
Groups: None
When I update my schedule, I updated my schedule manually for 50 % 100 % completed activities. But when I click the update progress the activities not yet even started show 5 % 10 % completed. Any friend may please guide?

Replies

Amreshwar Shukla
User offline. Last seen 1 year 23 weeks ago. Offline
Joined: 6 May 2003
Posts: 53
Groups: None
Dear Paul,
When you do automatic update, then P3 assume that everything are moving as per plan and update every activity as per initial base plan. If there are any deviations then update as mentioned by Arvin and Anoon.
Regards
Anoon Iimos
User offline. Last seen 2 years 32 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
some people are claiming that P3 is becoming obsolete while others still don’t have a clue! (including me);

P3 is using Duration; Resource Units and Costs

in updating P3 by just putting actuals, make sure you chose Duration

when you’re using Resources Units (which i supposed seldom used or never), make sure you got all the quantities!

when using Cost! I’m sure you’ll never get what you want!
Christian Adrian ...
User offline. Last seen 5 years 3 weeks ago. Offline
Joined: 3 Jun 2003
Posts: 193
Groups: None
Agree with Arvin.. if you’re updating your program just put all the actuals and press F9..
Arvin Dayday
User offline. Last seen 16 years 30 weeks ago. Offline
Joined: 18 May 2007
Posts: 12
Groups: None
Because

Update progress is an automatic way of updating a project. Meaning P3 quickly estimates activity dates, percent complete amounts, and remaining durations as of the new data date you specified by dragging the data-date line or by using the Progress Spotlight feature.