Total Planned % complete formula

F
Forum Guest 👤 Member for 17 years 4 months
P
Paul Harris 👤 Member for 25 years 2 months

When I am managing serious projects I calculate 4 percent completes:



1. The % of the original duration

2. The % of deliverables completed

3. The % of cost expended

4. The % of hours of labour or mobile equipment consumed



The comparison of the four percentage completes is very useful.



I normally use the P3 % complete for the % of duration, unlink % Complete and Remaining Duration and turn off all the Autocost Rules, I may enter the recorded cost and hours consumed and estimated to complete.



I use global changes to calculate the other three in custom data items.



There is an article titles The Practical Application of Earned Value which is on my web site which outlines some of these techniques.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Book Publishers, Training & Consulting

www.eh.com.au

F
Forum Guest 👤 Member for 17 years 4 months

[(sum of OD’s - sum of RD’s)/(Sum of OD’s)]*100 <---you missed it.

cheers

M
MK TSE 👤 Member for 24 years 3 months

According to Primavera KnowledgeBase 1999492110554, the formula is: -

(sum of OD’s - sum of RD’s)/(Sum of OD’s)

Forum Sponsor

Top Posters

bal aji
2 posts
Lee Mallek
23 posts
Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts