Hello all,
I have leveled 2 resources in a simple programme.
After levelling,the commencment of their associated activities are being delayed by 2 years from the data date.
I cannot see any other incriminating features of these activities:
- there are no constraints associated with these activities where these resources are assigned
- the resource and activity calendars are aligned
- the resource levelling and scheduling settings are completely blank, i.e. there are no unusual settings turned on.
WTF ?!?
Hi Jean-Michel,
how can you expect a reasonnable answer with such a few details?
* you should check the resource details, and specifically the Units and Price tab:
the by default Effective date is the 1st of january in the year the resource was created in the database; when the resources are leveled, P6 reschedules the activities according to this date; for example, the activity is scheduled to start dec 10, 2019 prior to leveling, and the resource is only effective jan 1st, 2020; the activity will be rescheduled as from this date after leveling
* you should check also the resource assignments in the other projects in you database
I hope this will help
Alexandre
Hi,
Kindly share the XER file?
Regards,