Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

HELP! Leveled Resources Delayed by Years ? WTF?

2 replies [Last post]
jean-michel albert
User offline. Last seen 3 years 40 weeks ago. Offline
Joined: 30 Mar 2015
Posts: 7
Groups: None

Hello all, 

I have leveled 2 resources in a simple programme.

After levelling,the commencment of their associated activities are being delayed by 2 years from the data date.

I cannot see any other incriminating features of these activities:

- there are no constraints associated with these activities where these resources are assigned

- the resource and activity calendars are aligned

- the resource levelling and scheduling settings are completely blank, i.e. there are no unusual settings turned on.

WTF ?!?

 

Replies

Raymund de Laza
User offline. Last seen 4 weeks 1 hour ago. Offline
Joined: 22 Nov 2009
Posts: 762

Hi,

Kindly share the XER file?

 

Regards,