Common Mistakes

4 replies [Last post]
Gowhar Mir
User offline. Last seen 5 years 35 weeks ago. Offline
Joined: 7 May 2018
Posts: 29
Groups: None

Planners of Planning Planet, what are the most common mistakes/oversights/errors that can be avoided at the begining of planning the prog and might prove to be consequential over the course of the time?

Replies

Zoltan Palffy
User offline. Last seen 29 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you can use this if you want to with the understading that your costs willbe DRIVEB by the manhours multiplied by the cost that you set for this resource.

i.e cost for the resource is $25/hr you add 4 hours to your units as manhours cost is $100 unless its an engineering function where you have a standard rate this wlll not work.

if it is set to YES then it wil prevent you from IMPORTING cost from excel since it is set to YES it will ignore the excel import.

Gowhar Mir
User offline. Last seen 5 years 35 weeks ago. Offline
Joined: 7 May 2018
Posts: 29
Groups: None

Thanks once again, Zoltan. Can you please tell what can be the effects of

on the resource calculate cost from units is checked (should not be)

Zoltan Palffy
User offline. Last seen 29 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

not turning on the times in your program thus 1 day durations span 2 days 

incorrect data date time

durations not in whole days

too many constraints

missing predecessors

missing successors

on the resource calculate cost from units is checked (should not be)

using incorrect calendars

resource assignment settings have activity can use the same resource more than once is check (should not be checked)

durations not set to fixed durations/units/time (if this is not set correctly and you add resources this could change your durations)

default units per time set to 0 (any thing diivided by 0 is o)

not correct start date and TIME

no must finish by date set in program 

Santosh Bhat
User offline. Last seen 21 weeks 5 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Put some thought into the data structures you want to use in the program, Activity ID's, Coding, WBS naming. You don't want to be making wholesale changes to these down the track.