Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Rough Calculation for manpower requirement

No replies
Pranav Patil
User offline. Last seen 7 years 35 weeks ago. Offline

Hi,

I am Pranav Patil, recently I have faced one interview. They asked me to calculate manpower required for a building RCC work whereas building has 4000 Sqm built up area for each floor. Total floors are 30 Nos. Scheduled completion is 15 Month.

I calculated manpower requirement as follows. Please suggest me if I wrong.

Total Nos. of floors -  30 Nos.

Completion time     -  15 Months

Cycle time to complete one floor  -  30/15 = 0.5 Months = 15 Days.

Carpenter Required 

Shuttering work quantum -  4000 x 1.5 = 6000 Sqm (Multiplied by 1.5 for shuttering for beams)

Days to ready slab shuttering = Cycle time / 2 =  15/2 = 7 Days

Per day productivity required = 6000/7 = 858 Sqm

Carpenter + Carpenter helper required = 858 /7 = 123 Nos.  (Productivity = 7 Sqm/day/(C+CH))

Barbender Required 

Concrete work qunatum = 4000 x0.15 = 600 Cum  (considered 0.15 thk of slab)

Quantum of reinforcement work = 600 x 0.1 = 60 MT

Per day productivity required  = 60/7 = 8.57 MT

Barbender + Barbender helper required = 8.57/0.15 = 57 Nos.

Total Manpower required:

Carpenter          = 123 Nos.

Carpenter helper = 123 Nos.

Bar bender         = 57  Nos.

Barbender Helper = 57 Nos.

Concreting helper  = 20 Nos.

Mason forfinishing = 2 Nos.

Total Manpower for RCC work = 382 Nos.

Please correct me if I wrong.