Difference between Start dates in P6

Member for

19 years

Hi Jitendrakumar,

The easiest way to understand or to get hint or information on P6 fields such as date is to activate the Hint-Help option by clicking the hint icon or press "Alt+F1". Then show all the columns of the fields that you wanted to get the information about then hover your mouse to each header of column that you need help. This very helpful option often neglegted by P6 users to use. See below:

Dates-in-P6

Member for

12 years 5 months

What is the most common format, doesn't it have to be Start, Finish, Late Start, Late Finish?  If you go to 6 columns doesn't that pretty much drive most non-schedulers crazy?  This is the only way to get the 100% "A" values and avoid confusion?

Member for

16 years 3 months

1. start is your current start date based on the data date and any predecessors not yet completed.

if the start date has an A next to it this is the actual start date of this activity 

2, The Actual start date is the actual start date that the activity started

3. Anticipated Start is the expected start date of the project, EPS node, or WBS level, used during the planning phase. This date is manually entered and is not affected by scheduling. An anticipated start date cannot be entered at the activity level.

4. Early start is the calculated during the forward pass and based on progress to date is the earliest date that the actviity can start.

5. Late start is calcuated during the backward pass and is the latest date that an activity can finish without being late.

6. External Early start is the early start for that activity that is LINKED to another project  

7. Planned start for an activity that has not started it is the date the activity is scheduled to begin. This date is set equal to the early start date. This date is not changed by the project scheduler once you apply an actual start date.

8. Remaining Early Start is the earliest possible date the remaining work for the activity is scheduled to begin. Before the activity is started the remaining start s the same as the palnned start. Once the activity has started, the remaining start is equal to the data date. When the activity is complete, the remaining start is blank.