Manpower loading

hi,

guys i have 30activities, which is finish to start.

and i have only 2men to complete all 33 activities.

how can i allocate just 2men.

My total manpower after allocation should show me 2men.

 

Thanks & Regards,

 

Vigeeth

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Assign those who will do the work, enter resource availability (two men) and then level project resources.

The software will organize the sequence of work so that at any time not more than two men will be used. It does not matter if your activity dependencies are FS or others, or no dependencies at all.

M
Mike Testro 👤 Member for 20 years 6 months

Hi Vigeeth

Just allocate 2 men to each of the tasks - when the logic is FS with no lead lags the histogram should show a straight line of 2 men allocated.

Best regards

Mike Testro

Forum Sponsor

Top Posters

James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts